Denver airport expansion delayed by 9-10 months (!)
denver.cbslocal.com/2022/02/26

A hot water pipe in the new part of Terminal B (United) flooded two floors of the building including electrical equipment. Cost to repair could be $50M (!) and won't be done until September or so.

Still not sure what caused the pipe to break.

Follow

@mhjohnson Worked on that project and the other concourse expansions. Haven't been on B-East in about a year though. Wish it had happened on the west side instead. Turner is so terrible to work with and Holder ran the east side so much better.